Question No : 6
You have a list of tasks entered into Microsoft Visual Studio Team Foundation Server (TFS) 2012. Each task has an estimated effort and assigned to a team member You have limited resources available. Due to external requirements, the start date and end date of the current iteration are fixed. Several of the tasks have dependencies on one another.You need to identify a critical path.What should you do? (To answer, move the three appropriate actions from the list of actions to the answer area and arrange them in the correct order.)