Question NO : 8

You are part of a scrum team that is trying to identify user stories to complete in the next sprint. You and the team need to select user stories for the next sprint.What should you do?

A. Have the product owner decide which user stories to complete within the sprint.
B. Have the scrum master decide which user stories to complete within the sprint.
C. Have the team decide which user stories to complete within the sprint.
D. Order the user stories by their story points. Select the top stories based on the team's velocity.

Answer: C

Explanation

The Sprint is a fixed-length event (30 days or less) in which the Development Team forecasts items from the Product Backlog and develops the items in the Sprint Backlog according to the acceptance criteria and their Definition of "Done."Professional Scrum Development with Microsoft Visual Studio 2012 p.169

Monday 4 June 2018

Valid And Updated 70-498 Exam Certifications Dumps Questions - Dumps4Download.in

Question NO : 7

Your development team uses the Microsoft Visual Studio Scrum 2.0 process template. The team has identified items from the product backlog for the next sprint.You need to ensure that the team has adequate capacity to complete the next sprint.Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)

A. Review the sprint Burndown chart.
B. Have the team assign hour estimates to each sprint task.
C. Review the sprint backlog.
D. Assign story points to each item in the product backlog.
E. Review the product backlog with forecast set to On to determine if the sprint can be completed based on the team's velocity.
F. Set each team member's per day capacity.

Answer: CEF

Explanation

Sprint Burndown charts can show the team how much work remains in the Sprint. These charts will often include an ideal trend line. This line represents the ideal rate at which the Development Team is able to complete all of the remaining effort, at a constant rate, by the end of the Sprint. Professional Scrum Development with Microsoft Visual Studio 2012 p.283 Prior to the Sprint, there shouldn't be any Task work items in the Sprint Backlog. Ideally, the Development Team creates its tasks during the Sprint Planning meeting and not before.Professional Scrum Development with Microsoft Visual Studio 2012 p.175 The Sprint Backlog contains those items selected by the Development Team plus a plan for delivering them. The Sprint Backlog shows the work remaining in the Sprint at all times.
Professional Scrum Development with Microsoft Visual Studio 2012 p.4 Story points should be already assigned to PBIs during identification for the sprint

Free Valid Microsoft 70-498 Exam Braindumps - 70-498 Exam Study Guide

Question NO # 9 Your development team uses Microsoft Visual Studio Team Foundation Server (TFS) 2012 to develop and support an enterprise-...