Question NO : 8
You are part of a scrum team that is trying to identify user stories to complete in the next sprint. You and the team need to select user stories for the next sprint.What should you do?
A. Have the product owner decide which user stories to complete within the sprint.
B. Have the scrum master decide which user stories to complete within the sprint.
C. Have the team decide which user stories to complete within the sprint.
D. Order the user stories by their story points. Select the top stories based on the team's velocity.
Answer: C
Explanation
The Sprint is a fixed-length event (30 days or less) in which the Development Team forecasts items from the Product Backlog and develops the items in the Sprint Backlog according to the acceptance criteria and their Definition of "Done."Professional Scrum Development with Microsoft Visual Studio 2012 p.169